The welding procedure and welding consumable of Double Floating roof oil storage tank

2022-07-20

1、Edge panel Welding

表1.jpg

图1.jpg图2.jpg

          Pic.1  Buttom Plate                                             Pic.2  Edge Plate Welding


2、Center Panel welding

表2.jpg

图3.jpg

Pic.3  Bottom Center Plate Welding


3、Edge Panel and Center Panel welding

表3.jpg


4、Heat treatmentpanel and Pipejoint welding

表4.jpg

图4.png

picture 4  the heat treatment plate and pipe joint


Welding Parameters: 130~180A/22V~26V

Elongation: 15~20mm

Gas flow: 15~20L/min

图5.jpg

Picture 5  Heat treatment plate and Pipe joint welding


5、Electrogas welding vertical wall panel

表5.jpg


图6.png

Pic.6  The Groove shape of Electrogas welding for Vertical wall panel


6、Submerged arc transverse welding of Circumferentialwall panel

表6.jpg


GWR-EA3/GXL-122;

GWL-H10Mn2/GXL-101H;

Welding parameters: 360~500A/25~30V

Elongation:20~30mm

图7.png

Pic.7  The Groove shape of Submerged Arc welding for Circumferential wall panel


7、Large fillet welding

表7.jpg

图8.jpg

Picture 8  The Sketch Map of Large fillet welding


图9.png

Picture 9  The traveler of Large fillet SAW welding